Winter Street Residential

Construction Impacts

Winter Street Prospective Construction Schedule

Phase 1a

  • 1000 Winter Multifamily

    • Construction: September 2027 - September 2029

  • Fitness Club

    • Construction: September 2028 - September 2030

Phase 1b

  • Townhomes

    • Construction: March 2028 - March 2030

Phase 2 & 3

  • 1100 Winter Multifamily

    • Construction: TBD

*Contingent on Special Permit approval, construction timelines are subject to change.

Construction Hours

Construction hours will be provided closer to the commencement of construction of each phase.

Current Work and Impacts

  • Traffic and pedestrian impacts - Details will be provided prior to commencement of construction.

  • Noise, parking, and abutter impacts

Upcoming Work & Impacts

  • Traffic and pedestrian impacts

  • Noise, parking, and abutter impacts